From: Kentucky Governors Office:
REOPENING OF NORTHBOUND U.S. 41 TWIN BRIDGE AT HENDERSON
FRANKFORT, Ky. – Kentucky Transportation Cabinet officials will reopen both northbound lanes of the U.S. 41 Twin Bridges at Henderson tonight. Governor Ernie Fletcher has been closely monitoring the bridge maintenance and painting project after leading a plan earlier this year that significantly minimized the impact to traffic during the closure.
“We are very pleased with the progress on the northbound bridge,” said Governor Fletcher. “Our priority was to complete the project in a timely and efficient manner and with as little disruption to traffic and area commerce as possible. We have accomplished that goal.”
The cabinet is working with the contractor to complete final inspections, and both lanes of the northbound bridge are expected to be restored and opened to traffic by tonight.
In April, the Governor asked engineers to reconsider an original plan that only allowed one lane of travel in each direction during the closure. As a result, a new plan was developed to run three 10-foot lanes of traffic on the southbound bridge, two for southbound traffic and one for northbound traffic. One lane of traffic was maintained on the northbound bridge. The plan allowed greater traffic flow and lessened the impact on area business.
Over the past two months, the contractor has moved work onto the southbound bridge. That work underneath the deck of the southbound bridge has only required nighttime lane closures.
After the northbound bridge is reopened to two lanes of traffic, the contractor will use the “extra lane” on the southbound bridge as a work platform to advance work underneath the southbound bridge at night. Traffic on the southbound bridge will remain restricted to two 10-foot lanes with a strictly enforced 10 mph speed limit and double fines in the work zone.
Construction will continue on the southbound bridge this fall as long as weather allows, and will continue on the superstructure of the southbound bridge in March 2008.
M & J Painting Company is the prime contractor on the $23 million bridge maintenance and painting project. Also known as the Bi-State Gold Star Vietnam War Memorial Bridges, the two structures carry approximately 40,000 vehicles daily across the Ohio River between Henderson and Evansville, Indiana. The northbound bridge was opened to traffic in 1932. It was last refurbished in 1983. The southbound bridge was opened to traffic in 1965. It was last painted in 1990.
Evansville Business Magazine's Todd Tucker joined with Executive
Director of the Economic Development Coalition
of Southwest Indiana Greg Wathen to discuss the proposed the fertilizer
plant in...
First Historic Newburgh Farm Market of the
year
presented by Romain GM
Opening Day, this
Saturday, May 25th!
Edgewater Grille Parking
Lot
Downtown Newburgh
8am-noonThose interested in at...
May is National Moving month, which
kicks off the busiest time of year for changing residencies. Your BBB
has received many complaints over the years regarding movers, and
scams relating to so to...
Blogger Mary Biever shares her journey and recovery after having a heart attack in December 2012. To learn more about Mary click here: http://www.marybiever.com/...